Contributing human and organizational factors for the collapse of a temporary supporting structure for the B-tower in Rotterdam

 Contributing human and organizational factors for the collapse of a temporary supporting structure for the B-tower in Rotterdam
Autor(en):
Beitrag für IABSE Congress: Challenges in Design and Construction of an Innovative and Sustainable Built Environment, Stockholm, Sweden, 21-23 September 2016, veröffentlicht in , S. 892-898
DOI: 10.2749/stockholm.2016.0879
Preis: € 25,00 inkl. MwSt. als PDF-Dokument  
ZUM EINKAUFSWAGEN HINZUFÜGEN
Vorschau herunterladen (PDF-Datei) 0.24 MB

In October 2010 the 70m high B-tower was being erected in the city centre of Rotterdam. The floors of the first five storeys were made as reinforced wide-slab floors. For the temporary support of t...
Weiterlesen

Bibliografische Angaben

Autor(en): (Delft University of Technology, Delft, The Netherlands Coenraedt B.V., Rotterdam, The Netherlands)
Medium: Tagungsbeitrag
Sprache(n): Englisch
Tagung: IABSE Congress: Challenges in Design and Construction of an Innovative and Sustainable Built Environment, Stockholm, Sweden, 21-23 September 2016
Veröffentlicht in:
Seite(n): 892-898 Anzahl der Seiten (im PDF): 7
Seite(n): 892-898
Anzahl der Seiten (im PDF): 7
Jahr: 2016
DOI: 10.2749/stockholm.2016.0879
Abstrakt:

In October 2010 the 70m high B-tower was being erected in the city centre of Rotterdam. The floors of the first five storeys were made as reinforced wide-slab floors. For the temporary support of the precast planks during casting of the concrete scaffolding was used. In the floor plan a void was foreseen, resulting in an increased storey height. At this position the scaffolding had a height of approximately 11.50m. During casting of the floor, the temporary structure collapsed, resulting in 5 injuries among the construction workers.

Investigation from the Dutch Safety Board revealed that a large number of stability braces was omitted in one direction, resulting in instability and collapse of the temporary structure. This omission had been noticed, but because of unclarity in responsibilities no follow up was given to this warning.

This paper describes the structure of the temporary scaffolding, will reveal the technical cause and will pay attention to underlying human and organizational factors that contributed to the failure of this structure. For these contributing factors a theoretical framework with potential influencing factors for structural safety is used.

Stichwörter:
Versagen Einsturz